Building a Ceramic Art Studio
We decided
to begin building a ceramic art studio here at Spherical Block, LLC in Alfred,
NY. This facility would be modestly sized, and made of concrete block masonry
construction. We decided to utilize and showcase Spherical Block’s technology
by making the roof from three domes.
First we
decided on a design, which was to be a central square room, flanked on either
side by smaller square alcove rooms. The central dome would be a 16 ft diameter
dome, and the alcoves would be covered by smaller, 8 ft diameter domes. All
vertical walls would be 8 ft high. This would provide the building with an
open, airy space and create a natural, flowing symmetry. Here is an early
sketch of the building, which was used on the building permit application.

Having a
design in hand, we obtained a building permit and began site preparation. The
first step was to excavate a trough large enough to pour the footer with
concrete. In our area of NY, winters can get brutally cold. This necessitates a
deep footer, 4 ft. below the surface to prevent heaving from deep freezes. We
hired an excellent local contractor, John Halsey, he excavated the entire
footer in around half a day’s work. Here are some pictures of the formwork for
the footer being assembled in the excavated trough. The form had rebar placed in it and was
filled with concrete.


A ‘stem
wall’ was built on top of the footer, bringing the foundation up to the level
of the ground. This stem wall was reinforced with vertical rebar placed in the
core hole of blocks and poured (grouted) in place. The rebar we used was FRP
basaltic rebar (Fiber Reinforced Plastic). We used #3 rebar, 3/8 inch diameter.
It is lightweight, flexible, non-metallic so it never rusts, and is 3.5 times
stronger than steel in tension. Basaltic rebar is especially corrosive
resistant (better than fiberglass rebar). Reinforcement was located at all
corners, and at 4 ft horizontal spacing along the wall lengths. Additionally,
horizontal reinforcement was included as ‘ladder’ wire enforcement in the
horizontal mortar beds of the stem wall.

The mortar
joints are sloppy on the stem wall: they are underground and not seen. We then
filled the gaps of the excavated area to provide a level surface around the
stem wall. I should note that I am not a mason, nor a contractor. I experiment
with novel masonry systems.

The vertical
walls were then begun. I built this all by myself; lots of work, mixing mortar
and moving block alone.

Next, we
levelled the dirt floor and installed a rigid foam (expanded polystyrene) so
that we could install a radiant heated floor system. ‘Pex’ plastic piping was
arranged in the rigid foam floor, and a concrete floor was poured on top of it.
Two loops of pipe were installed for the radiant heating floor system.



The vertical
walls were assembled, and lintels were poured over the six windows and the
door. FRP rebar was used in all lintels.



Once all
lintels were cast, the windows were installed. We used double-hung, quality
insulated windows.

In order to
fit round domes on top of square rooms, we cast 8-inch thick reinforced
pendentives. We needed pendentives for both the 8-ft alcove rooms and the 16 ft
central rooms. The larger pendentive is not poured yet.


Once the
pendentives were poured, we assembled the smaller 8 ft domes on top of them.
Both domes were assembled fairly quickly, in just a few hours. I was working
alone, tending myself and moving all block. These are assembled as a truncated
icosahedron, made from pentagons and hexagons, like a soccer ball: where the
white patches are hexagons and the black patches are pentagons.
On the
inside of the building, we assembled arches as entryways into the two alcove
rooms. This creates an open, elegant interior space. The areas above the
masonry arches were poured with concrete.





We had a
custom arched door made, and installed a masonry arch over the top. It
contributes to the ‘arched’ look and feel of the whole building.

This is the
building in its current state, at the end of November 2026. With cold weather
rapidly approaching, it looks like we’re done for the season. Construction will
resume in the Spring. It’s been a fun project so far! We are eager to make
ceramic art here next year.

Built like a bunker. An archy bunker.